Contents of the Level Down Projects Future Revenue Screen
Use this screen to run a report that displays all projects projected revenue.
The report summarizes budgeted revenues by WBS and displays Budget and EAC revenues for all POP. The report on this screen displays budgets/EACs that are marked as final on the Project Budgets / EACs screen.
Contents
Field | Description |
---|---|
Budget Type |
If you selected the Budget or Variance report type, select one of the following from the drop-down list:
Note: EAC displays in the drop-down list only if an EAC exists for the project.
|
Timing |
If you selected a budget type of EAC, select one of the following timing options:
|
Cost Type |
To filter the report by cost type, click to select a cost category. Choose from the following cost types:
|
All Sub-Tasks |
Select this check box to display all tasks under the current project level selected. |
Project ID |
Enter, or click to select, the project ID. |
Subtasks
After you select the Project ID and set other report options, click the following links to display future revenue or revenue breakdown information:
- Level Down Projects Future Revenue: Click this link to display future revenue.
- Revenue Breakdown: Click this link to display revenue breakdown for the entire period of performance.
- Related Topics:
- Percent Complete Revenue Calculation
Project Budgeting includes a percent complete revenue calculation that can determine forecasted revenue (into the future) for projects with revenue formulas of EAC, ETC, or % complete. - Subtasks of Level Down Projects Future Revenue
Level Down Projects Future Revenue has several subtasks.