Manage Period Days
Use this screen to enter the days per period that you would like to use to spread budgeted data.
This screen is used in conjunction with the Spread Budgets Based on Days check box on the Configure Project Budget Settings screen. If you did not select the check box, you can enter data in this screen, but it is not used. This screen allows you to spread budget data by month based on the number of days in each month. The selection on the Configure Project Budget Settings screen is a system-wide selection.
You should populate this screen before entering budgets on the Manage Project Budgets and ETC screen. Costpoint uses the days per period in this screen when you use the "spread" function in the subtasks of the Manage Project Budgets and ETC screen. The amounts are spread over the periods based on the weighted number of days in the period.
- Related Topics:
- Display the Manage Period Days Screen
You access the Display the Manage Period Days screen from the Projects domain. - Contents of the Manage Period Days Screen
Use the fields and options to configure the Manage Period Days screen. - Table Information for the Manage Period Days Screen
Changes to the Manage Period Days screen update the PROJ_BUDGET_DAYS table. - Spread a Budget Over the Days in a Period
You can spread a budget over the days in a period rather than over the period itself.