Total Ceilings Tab
Use this tab of the Manage Project Revenue Calculation Value History screen to view revenue calculation value history of the total ceilings placed on the contract and funded values of the project.
You can also use this tab to update the audit tables to specify or modify the ceiling codes used for the signed/funded total, cost, and fee values of the project entered on the main screen.
This tab is populated with information generated by the Compute Revenue process if you have run Compute Revenue for this project.
Valid ceiling codes are R (Revenue), B (Billing), A (All), or N (None).
Funding Info
Use the fields in this group box to view or modify ceilings on the funded value of the project.
Field | Description |
---|---|
Total |
This field displays the ceiling code for the funded total value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Total |
This field displays the sum of all funded total modifications for this project branch and its lower levels. |
Fee % |
This field displays the fee percent, which is calculated as the Fee value divided by the Cost value. |
Cost |
This field displays the ceiling code for the funded cost value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Costs |
This field displays the sum of all funded cost modifications for this project branch and its lower levels. |
Fee |
This field displays the ceiling code for the funded fee value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Fee |
This field displays the sum of all funded fee modifications for this project branch and its lower levels. |
Award Fee |
This field displays the cumulative funded award fee. The funded award fee is summarized at the level of the project displayed in the Project field and all levels below. This amount includes all modifications for this project. |
Value Info
Use the fields in this group box to view or modify ceilings on the award value of the project.
Field | Description |
---|---|
Total |
This field displays the ceiling code for the awarded total value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Total |
This field displays the sum of all awarded total modifications for this project branch and its lower levels. |
Fee % |
This field displays the fee percent, which is calculated as the Fee value divided by the Cost value. |
Cost |
This field displays the ceiling code for the awarded cost value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Costs |
This field displays the sum of all awarded cost modifications for this project branch and its lower levels. |
Fee |
This field displays the ceiling code for the awarded fee value of the project. For new records or if you want to modify the current ceiling code, enter any of the following valid codes:
|
Fee |
This field displays the sum of all awarded fee modifications for this project branch and its lower levels. |
Award Fee |
This field displays the cumulative contract value award fee. The contract value award fee is summarized at the level of the project displayed in the Project field and all levels below. This amount includes all modifications for this project. |