Period Summary Subtask

This non-editable subtask summarizes the data entered in the main screen by the period selected.

Contents

Field Description
Budgeted Units To Deliver

This field summarizes the budgeted number of units by period for the selected period.

Estimated Total Costs

Costpoint calculates this field by multiplying the budgeted Number of Units per subperiod by the Estimated Cost Per Unit. Costs are then summarized for the period selected.

Estimated Profit

Costpoint calculates this field by multiplying the Budgeted Contract Price by budgeted Number of Units to deliver for the given period, and then subtracting the Estimated Total Costs to arrive at an estimated profit amount.

Budgeted Contract Price

This field displays the price per unit budgeted for the contract, as entered on the Project Unit Pricing subtask of the Manage CLIN Information screen.

Average Cost Per Unit

This field displays the average cost per unit for the period selected.

Average Price Per Unit

This field displays the average price per unit for the period selected.

Refresh

Click this button to refresh this subtask after making changes on the main screen.