Project Subcontractor Status Report
Use the Project Subcontractor Status report to monitor and manage subcontractor labor and other subcontractor costs for existing projects. To provide a more complete picture, the report includes the cost of unfulfilled materials and services commitments from Costpoint.
For each subcontractor resource, the report displays the following:
-
Inception-to-date (ITD) actual burdened cost through the period preceding the current period in Costpoint Planning
-
Actual burdened cost for the current period in Costpoint Planning (<current period end date> Actuals column)
-
Burdened commitment cost
-
Total cost to date (ITD actual burdened cost + Current period actual burdened cost + Commitment burdened cost)
-
Estimate-at-completion (EAC) burdened cost
-
Balance remaining (EAC burdened cost – Total cost to date)
The report displays subtotals for each project level and totals for the report as a whole.
- Related Topics:
- Options
When you generate this report, you can enter all or part of a project ID. - Reconcile Report Data
There are guidelines on how to reconcile data on this report with data in Costpoint Planning.