Manage CSSR Budgets
Use two Costpoint screens to enter budget figures into the C/SSR report: Maintain C/SSR Budgets (this screen) or Import CSSR Budgets.
Use this screen to enter the budgeted costs of scheduled work and work performed. You can upload your budgets from a file using the Import C/SSR Budgets screen. Information from this screen prints in columns 7.(2) and 7.(3) of the C/SSR.
To ensure correct budget figures, use this screen before creating the C/SSR tables.
- Related Topics:
- Display the Manage CSSR Budgets Screen
You access the Manage CSSR Budgets screen from the Projects domain. - Contents of the Manage CSSR Budgets Screen
Use the fields and options to configure the Manage CSSR Budgets screen. - Table Information for the Manage CSSR Budgets Screen
Changes to the Manage CSSR Budgets screen update the PROJ_CSSR_BUD table.