Contents of the Manage CSSR Budgets Screen
Use the fields and options to configure the Manage CSSR Budgets screen.
Identification
Field | Description |
---|---|
Proj |
Click to select the project for which you are entering budget data. |
C/SSR Budget Details
Click to add data to this table.
Field | Description |
---|---|
WBS Proj |
Enter, or click to select, the project using the Work Breakdown Structure (WBS) of the project tree. |
FY |
Enter the fiscal year for this project's row of budgeted data. |
Pd |
Enter the period for this project's row of budgeted data. |
Subpd |
Enter the subperiod for this project's row of budgeted data. |
Work Scheduled |
Enter the work scheduled amount for this project's row of budgeted data. This amount prints in item 7.(2)a. of the C/SSR. |
Work Performed |
Enter the work performed amount for this project's row of budgeted data. This amount prints in item 7.(3)a. of the C/SSR. |
COM on Work Scheduled |
Enter the Cost of Money (COM) on work scheduled for this project's row of budgeted data. This amount prints in item 7.(2)b. of the C/SSR. |
COM on Work Performed |
Enter the Cost of Money on work performed for this project's row of budgeted data. This amount prints in item 7.(3)b. of the C/SSR. |
G & A on Work Scheduled |
Enter the General & Administrative (G&A) costs on work scheduled for this project's row of budgeted data. This amount prints in item 7.(2)c. of the C/SSR. |
G & A on Work Performed |
Enter the General & Administrative costs on work performed for this project's row of budgeted data. This amount prints in item 7.(3)c. of the C/SSR. |