Project Rollup Notes

The report rolls up revenue for backlog projects to the project level that you specify on the prompts screen.

Note the following about the project rollup option:

  • The report does not roll up revenue for new business projects. Those amounts are always displayed at the level they are entered in Costpoint Planning.

  • If you do not filter the report for specific projects, and if revenue for any projects has been budgeted at a higher project level than the project rollup level you specify on the prompts page, the report displays the total of that additional revenue in a separate detail row without a project ID. It also includes that revenue in the organization subtotals so those subtotals reflect the total projected revenue for the organization.