Update Prior Year History
Use this screen to update the prior year project costs (hours, units, billing value, Cobra costs) for the fiscal year specified.
This process updates the Manage Prior Year Cost and Revenue screen, which contains data for direct costs, indirect costs, and revenue incurred prior to the current fiscal year. The data on the Manage Prior Year Cost and Revenue screen is used to calculate cumulative columns on projects reports and inception-to-date revenue. Use this process after you have completed the closing process for the fiscal year before you compute revenue for the new fiscal year. Projects reports and any inception-to-date revenue calculations are incorrect if you do not run this process at the proper time.
The program copies data from the PROJ_SUM and PROJ_BURD_SUM tables into the PSR_PY_SUM table using rates (actual or target) that are selected in this screen. For prior year units, Costpoint copies the UNITS_USAGE_HS table into the PY_UNITS_PRICING table and, for labor, copies the LAB_HS table into the PY_PROJ_LAB_HS table. The data in the PROJ_GOAL_DETL table is copied into the PY_GOAL table during this process.
Run this screen as part of your fiscal year close process. You can optionally run it again after audit and other post-year-end adjustments are made to finalize prior year information. You should finalize project costs and revenue before you execute this screen. The utility deletes existing rows from the prior year tables and then inserts new data, based on the criteria you have selected. Therefore, you can execute it as many times as necessary.
If you are computing revenue for a new fiscal year, make sure that you executed the Update Prior Year History process to update the prior year's data before you compute revenue for the new year. Otherwise, your revenue calculations for the new fiscal year could be misstated. Among its many functions, the Update Prior Year History program combines the current year project tables (PROJ_SUM and PROJ_BURD_SUM) with the prior year project tables (PSR_PY_SUM and PSR_PY_BURD_SUM). The prior year project tables are the source for prior year cost and revenue amounts for the Compute Revenue process. If you have not updated the prior year tables, revenue calculations for the new fiscal year could be incorrect.
- Related Topics:
- Display the Update Prior Year History Screen
You access the Update Prior Year History screen from the Projects domain. - Contents of the Update Prior Year History Screen
Use these fields and options to configure the Update Prior Year History screen. - Table Information for the Update Prior Year History Screen
Changes to the Update Prior Year History Screen update several tables.